From the project manager on 7/31/17:
As of today, all the pulverizing and milling work has been completed along with the replacement of the new culverts (within the Town of Scott). In the coming week, Northeast Asphalt will be completing the undercutting work and fine grading. Paving is currently scheduled for the week of August 7th, which is anticipated to take seven working days.
Construction Season is Here!
Abbott Drive and State Highway 144 are both slatted for reconstruction this summer. Both projects will be starting in July, but check back here periodically for updates. Please be courteous and mindful of the workers, obey all traffic signs, and always use marked detours. Your safety is number one to us!!